2007 saw the completion of 2 highly prestigious projects for Hemsec Installations:
Terminal 5, Heathrow; Firewall package and
Monkhill Confectionary, Pontefract; Factory rebuild.
Working Respectively for Mace Solutions and Bovis Lendlease, both projects were completed within budget and on programme with a combined value in excess of £4.5 Million pounds.
A number of other significant projects were also completed successfully during this period including a total factory refurbishment and extension for Tulip International, Kings Lynn, working with R.G. Carter Ltd. (Contract value in excess of £1 Million pounds.)
Hemsec Installations continues their successful working partnership with Clegg Food Projects Ltd resulting in 2 further major successes:
Greggs Bakery, Cambuslang, Scotland; New Bakery Facility.
Direct Table Foods, Bury St Edmunds; New Bacon Processing Facility. (Contract value on each project was
in excess of £1 Million pounds.)

Working wih Langwith Builders, Hemsec Installations commenced and completed a new Fruit packaging facility in Spalding, Lincolnshire for Worldwide Fruit Ltd. (Contract value in exess of £500,000.)
This project was again completed in
budget and on programme.
During the latter part of 2007, Hemsec Installations commenced work on a number of major new projects including;
Kerrygold PLC, Leek, Staffordshire (New cheese processing facility)
Direct Table Foods, Bury St Edmunds. (Phase 2, Bacon processing facility)
Woodhead Brothers, Spalding. (Abbatoir extension and refurbishment.)
|